The Problem with Average Lead Times (And What Good Safety Stock Requires)

Blog Article

The Problem with Average Lead Times (And What Good Safety Stock Requires)

A supplier that averages a lead time of two to three months on an item can deliver one order in a week and the next in ninety days. The average describes a supplier's typical delivery time, not the range of delivery times a buyer has to plan for. Safety stock sized to average lead time leaves the buyer short when a delivery runs late, and holding extra when it arrives early so the buffer has to reflect how variable the lead time is, not only how long it is on average.

Why does an average lead time fall short?

An average blends every delivery into one number, and the two deliveries that cost money are the ones it hides. The early order arrives before it is needed and sits in inventory, adding carrying cost. The late order arrives after a stockout, and the shortfall shows up as lost sales or expedited freight. Two suppliers can share the same average and still call for very different buffers, because one delivers consistently and the other swings between a week and ninety days.

What does “good” safety stock require?

Well-calculated safety stock starts from three inputs: how much demand varies, how much lead time varies, and the service level the business wants to hit. Calculating safety stock off the average lead time alone leaves out how much lead time varies. Good safety stock also weighs what each service level target costs, so teams choose the target deliberately instead of by habit. The buffer a distributor holds against a supplier with consistent deliveries should be smaller than the buffer held against a supplier with uneven deliveries, and that difference only appears when variability is part of the calculation.

Blue Ridge can size safety stock from the lead times suppliers deliver

Blue Ridge Replenishment Planning calculates safety stock from three inputs:

  • Demand variability. How far actual demand departs from the forecast. A forecast plus the probabilities behind it feeds the calculation, so products with less predictable demand carry more cover and steadier products carry less.
  • Lead time variability. How much a supplier's delivery time differs from one order to the next. Variability is its own input to the safety stock calculation, and it can be set at the sourcing network or the product-location-supplier level. Lead Time Forecasting learns each supplier's lead time and its variability from the distributor's receipts at the product-location-supplier level, and safety stock adjusts to the lead times suppliers deliver, not the lead times they quote.
  • Target service level. The share of demand the business aims to fill from stock. The target sets how much cover the calculation builds in, and Cost of Service Analysis (COSA) models what different targets cost, so teams can set them with the cost in view.

With Lead Time Forecasting, the result is safety stock built on what suppliers deliver and how that varies, not on a single quoted or average lead time.

Talk to a Blue Ridge expert to learn more.

You might also like

View all related

How Lohmiller Plans for Seasonal Demand: From a 30-Day View to a Full Year

Read more

Configuration vs. Customization: How to Evaluate a Supply Chain Planning Platform

Read more

Built on Databricks: What a Modern Data Foundation Means for Planning at Scale

Read more

KEEP EXPLORING

Beyond the blog

Webinars when you have an hour. Guides and reports worth bookmarking. Customer stories you'll want to share. The full library is here.

Explore the platform
Explore the Platform

Get Started

See what enterprise-grade intelligence can do for you

New to Blue Ridge? Let’s talk about how we can help free trapped capital, protect service levels, and give your team back hours lost to work that should run itself.

Talk to an Expert